Hillsborough's AI data center pause awaits new board
Add Axios as your preferred source to
see more of our stories on Google.

Illustration: Brendan Lynch/Axios
The Hillsborough County Commission's new Democratic majority takes office Tuesday, and waiting for it is a question the outgoing board put off: Should the county pause AI data centers?
Why it matters: Data centers have become the face of the AI backlash. More than 300 local moratoriums have passed nationwide, and nearly half of Americans support pausing construction, one poll found.
Driving the news: Commissioners punted a vote last week that would have kicked off a process to temporarily ban AI data centers, leaving the decision to the incoming board taking office tomorrow.
- If commissioners move forward, the county would schedule two public hearings before voting on an ordinance that would halt data center development in unincorporated Hillsborough for one year.
- The moratorium would take effect after Oct. 1. Commissioners also directed county staff to explore permanent regulations, including restrictions on using drinking water for cooling.
Between the lines: A state law intended to help communities rebuild after Hurricanes Debby, Helene and Milton prohibits affected counties from proposing or adopting stricter land-use rules until October 2027.
- The county's proposed ordinance accounts for the law, but its delayed start leaves it vulnerable to new restrictions the state Legislature could adopt when it convenes in March.
- Gov.-elect Byron Donalds, meanwhile, has ruled out supporting a statewide moratorium on data centers but says counties and cities should retain the authority to impose their own.
Yes, but: Even without a moratorium, the county's land development code doesn't list data centers among its permitted uses, county staff said.
- Any developer would need commissioners to rezone the land, a process that takes at least six months.
- So far, no one has applied.
Zoom out: In Tampa Bay, Citrus, Pasco, Hernando and Sarasota counties have already enacted temporary bans.
- Pinellas County instead adopted a resolution in September saying its land development code already bars large data centers because — like Hillsborough's — it doesn't list them as a permitted use.
- Tampa City Council has scheduled hearings on its own moratorium for Dec. 3 and Jan. 7. It also directed staff to stop accepting data center applications in the meantime.