New Orleans delays Lafitte Greenway expansion, other projects
Add Axios as your preferred source to
see more of our stories on Google.

The Lafitte Greenway expansion from Alexander Street to Canal Street is on hold. Photo: Bryan Tarnowski/Bloomberg via Getty Images
The Lafitte Greenway expansion is on hold after New Orleans officials cut $35 million for infrastructure projects due to the city's fiscal crisis.
Why it matters: The cut further delays the expansion along with other long-awaited neighborhood improvements as the city tries to shore up its finances.
The big picture: Delaying the Greenway expansion saves about $429,000, a city spreadsheet shows.
- The city also delayed a walking path on Peoples Avenue ($300,000), the Hollygrove Greenline Trail ($140,000) and restoration efforts for the Carver-Penn baseball field ($75,000).
- Other green space and cemetery restoration projects were delayed, along with a $1 million plan to reduce greenhouse gas emissions from municipal buildings.
- The projects are just delayed, not canceled, public works director Steve Nelson told the City Council recently. "It's still painful."
Zoom in: The measure is necessary to ensure the city is "fiscally stable," Nelson added.
- The $35 million will be reallocated from 2026 bonds and converted to cash, he said.
- "This is part of the challenging reality that we face in order to meet our general fund obligations," he said.
By the numbers: Some of the bigger cuts include…
- Tullis Drive ($5 million). The project will advance in phases instead.
- Holiday Drive at General De Gaulle Drive ($4 million). Construction funds aren't needed until 2028.
- Uptown quiet zones ($1.1 million). Construction is delayed.
- Old VA hospital building renovations ($1.3 million). The city says a federal grant for this project was canceled.
Zoom in: Several of the cuts are because the scope came in lower than the original budget, the spreadsheet shows.
- Example: The scope for North Miro Street construction, from Elysian Fields to Almonaster Avenue, came in $4 million under budget.
- The same was true for Fats Domino Avenue ($3 million), Lake Forest Boulevard ($2.5 million) and Bienville Avenue ($1.5 million), the data shows.
Catch up quick: The Moreno administration inherited a fiscal crisis and has furloughed employees, cut programs and borrowed money to keep the city running.
- Mayor Helena Moreno initially sought to get approval from the state for another loan, but withdrew the request amid a tense political climate.
- The infrastructure cuts were announced after that as leaders look to find more than $100 million in savings.
What's next: Moreno says she has already begun touring the city and meeting with residents in an effort to shape priorities for her budget proposal, which she'll present in October.