Mar 10, 2022 - Development

Why Mecklenburg County is spending millions on a mile of greenway

Four Mile Creek Greenway (photo: Bri Crane/Axios)

Mecklenburg County is spending nearly $8 million to add about a mile of new outdoor space in south Charlotte that will extend an already popular greenway system.

The new section will begin at Johnston Road, where the Four Mile Creek Greenway and McAlpine Creek Greenway come together, and extend upstream up Highway 51.

Currently, the project is in its design phase. Construction will begin in about a year and is set to be completed by 2024.

Why it matters: “Greenways continue to be our No. 1 requested amenity within our system anytime we do a large scale survey,” said Bert Lynn, capital planning division director for Mecklenburg County Park and Recreation.

The community uses these systems for recreation, of course — on any given day, you’ll find hundreds of cyclists, runners and dog- and stroller-walkers on the city’s greenways. But when these systems grow long enough, people often bike long distances to get to work and other destinations, Lynn noted.

“What we’ve found is once a system gets more than four miles of connectivity, the use begins to expand beyond recreation,” he said.

  • Currently, the McAlpine/McMullen/Four Mile system is the busiest in the region, Lynn said. It’s roughly 6.5 miles now and will be about 7.5 miles when the work is complete.


Data: Mecklenburg County; Chart: Axios Visuals

Zoom out: Using bikes, scooters, our own feet or any other non-automobile method to get from A to B is particularly important locally as Charlotte tries to become less car-reliant.

Did you know: The city is responsible for planning and building the Cross Charlotte Trail, which’ll eventually be a 40-mile system stretching from the South Carolina state border up to the Cabarrus County line.

  • The county maintains and operates greenway projects. The Cross Charlotte Trail intersects with chunks of greenway, though, so the county will maintain portions of it once they’re completed.

Details: The new greenway will have more boardwalk than is typical because it goes through wetlands, Lynn said. It’ll have at least one major bridge over the creek, too.

  • The project’s total budget is $7.8 million. Much of the funding ($5.77 million) is provided through a federal transportation grant through NCDOT, according to the county.
Four Mile Creek Greenway between Johnston Road and Bevington Place trailheads. Photo courtesy of Mecklenburg County

“It’ll be very similar to our other projects. It’ll be within the floodplain, parallel to the creek, linking in to and extending connectivity to an existing system. Then it’ll provide additional access points to single-family (neighborhoods), multifamily (developments) and some office along this stretch of the project who don’t currently have access to the greenway,” Lynn said.

avatar

Get more local stories in your inbox with Axios Charlotte.

🌱

Support local journalism by becoming a member.

Learn more

More Charlotte stories

No stories could be found

Charlottepostcard

Get a free daily digest of the most important news in your backyard with Axios Charlotte.

🌱

Support local journalism by becoming a member.

Learn more