Local pushback mounts, but AI buildout surges on
Add Axios as your preferred source to
see more of our stories on Google.


A powerful backlash against AI and data centers has been building for months, fueling local moratoriums and political opposition, but also fears that the $10 trillion infrastructure buildout could hit a wall.
Why it matters: The stakes extend far beyond the U.S. Any backlash that slows the AI boom could have global consequences, with the futures of politicians, economies and nations increasingly tied to the race for technological supremacy.
The big picture: Despite more than 300 local moratoriums, U.S. data center development is moving at a blistering pace. The industry may add more than 50 gigawatts of capacity in 2027, according to research firm SemiAnalysis.
- Construction on nearly half of that capacity is already at an advanced stage, and developers have signed $1 trillion in leases to support the expansion, SemiAnalysis says.

Between the lines: The buildout is far from friction-free. Political, regulatory, supply and environmental hurdles are delaying some major projects.
- In New Mexico, Oracle took steps to protect itself from steep costs tied to delays of the $165 billion Project Jupiter stemming from local opposition, permitting roadblocks and power supply challenges.
- In Texas, an audit ordered by Gov. Greg Abbott is adding months of delays for projects seeking to connect to the state's electric grid.
- In New York, an executive order pausing environmental permits for larger facilities has delayed nearly 1 gigawatt of capacity, according to SemiAnalysis.
The bottom line: Local opposition and mounting regulatory scrutiny are creating isolated bottlenecks, but they have yet to derail the broader infrastructure boom.
- The midterm elections will offer an early test of whether growing voter resistance could become a more formidable obstacle.