Courthouse plans come into focus
Add Axios as your preferred source to
see more of our stories on Google.

Madison County is moving closer to finalizing the logistics of temporary facilities as it works to construct a new $100-million courthouse.
Why it matters: Progress is being made, and key decisions are imminent, on a project that will change the face of downtown Huntsville for the next 50 years and beyond.
The latest: At a special meeting Friday, the Madison County Commission heard from architect Goodwyn Mills Cawood and engineering firm Volkert on how the county can continue to keep its courts and administration running during construction.
- Commissioners had been waiting to hear cost details for the temporary relocation before making the final decision on whether to pursue construction of a single courthouse at the current site, or to construct two separate buildings, said District 5 Commissioner Phil Riddick.
- That cost, per details presented Friday, is just under $10 million, and Commission Chair Rex Vaughn said "most of our commissioners have kind of rallied around the idea of one big courthouse."
- That decision is expected to be made at the Commission's next meeting this Wednesday.
Zoom in: That will likely mean renovations at 101 Holmes Ave., the old federal courthouse, and the use of 320 Fountain Circle, the former city Public Service Building.
- Numbers presented Friday showed that the original estimate of about $24 million for the temporary move space is down to around $15 million.
- With the $5 million toward the renovation of 101 Holmes Ave. from the city's latest Tax Increment Financing District, that comes down to just under $10 million, per Mark Coyle, with GMC.
By the numbers: Of that, about $4.6 million is set to be spent renovating the building on Fountain Circle and $9.9 million total, without subtracting the $5 million from the city, for the Holmes Avenue building.
Zoom out: Business owners on the square voiced their concerns about disruptions to operations during a long demolition and construction schedule.
Driving the news: The county is still exploring options for the lease or purchase of another building — the details of which haven't been released — that would mean the Fountain Circle building wouldn't be needed, per Kerry Wilkerson with Volkert.